PdM Program Guide · 07 · Rollout

Rollout, alarms, workflow and KPIs

A program proves itself in the months after installation: alarms that people trust, findings that become planned work, and numbers that show the value. This page covers how to get there.

Beginner to intermediate15 min readInteractive

Pilot first

A pilot tests the whole chain, from sensor to work order, on a manageable scale before you commit budget to the whole site.

  • Scope: 20 to 50 assets in one area, mostly tier A and B, with a mix of types and some known bad actors.
  • Duration: 3 to 6 months, long enough to see real faults develop and be repaired.
  • Success criteria written up front: for example, at least three confirmed catches with recorded cost avoided, fewer than one false alarm per 10 assets per month after tuning, and every alert reviewed within the agreed time.
  • Technical checks: radio coverage, battery drain against forecast, data completeness, integration with the maintenance system.

Baseline, then alarm

After installation, collect two to four weeks of data across the normal range of operating conditions before trusting alarms. Then build alarms in layers:

LayerHow it worksStrength
Severity limitsBroad-band velocity compared with machine-class limits such as those in the ISO 20816 seriesSimple, comparable across sites; a sensible absolute ceiling
Statistical baselinesAlarm when a value moves several standard deviations from the asset's own baseline, or rises by a set ratioAdapts to each machine; catches change early
Band and fault-frequency alarmsEnergy in bands around bearing, gear or vane frequenciesPoints to a likely cause
Rate of changeAlarm when the trend slope exceeds a limitCatches fast-developing faults
Machine learningAnomaly scores on many features at once, conditioned on operating stateFewer false alarms in variable operation; scales to many assets

Use two or three alarm levels (for example alert and danger) with clear meanings and response times, and set the sensitivity by criticality: tighter on tier A, looser on tier C. Review false and missed alarms every month for the first six months.

From alert to work order

  • Write recommendations that a planner can act on: "Replace motor non-drive-end bearing within 4 weeks; outer race defect, moderate severity; check alignment on reassembly."
  • Give every recommendation a priority mapped to your work order system, and track it to closure.
  • Record what was found when the machine was opened. That feedback confirms the diagnosis, labels data for machine learning, and is the evidence for the value of the program.
  • Hold a short weekly review between condition monitoring, planning and operations for open findings.

Roles and skills

RoleResponsibilities
Program ownerGoals, budget, KPIs, cross-department alignment
Reliability engineerCriticality, failure modes, strategy, root cause analysis
Condition monitoring analystData review, diagnosis, recommendations, alarm tuning
TechniciansSensor installation and mounting quality, routes, corrective work, as-found feedback
Planner and schedulerTurn recommendations into scheduled work with parts and permits
OT and ITNetwork, gateways, security, integration, data retention
Data scientist (as the program grows)Models, feature pipelines, monitoring of model performance

Analyst competence is recognised internationally through ISO 18436-2, which defines four categories of vibration analyst from basic data collection (category I) to advanced diagnostics and program leadership (category IV). Other parts of ISO 18436 cover lubrication, thermography and ultrasound practitioners. Even with machine learning, someone with category II or III skills should review findings on critical assets.

KPIs that show whether it works

KPIDefinitionDirection
CoverageShare of tier A and B assets on the programUp, towards 100% of tier A
Data completenessShare of scheduled measurements actually receivedAbove 95%
Catch rateFailures detected before functional failure ÷ all failures on monitored assetsUp
Mean warning timeAverage time between first alert and functional failure or repairUp
False alarm rateAlerts not confirmed by review or inspection ÷ all alertsDown
Recommendation closureRecommendations completed by the due dateUp
Planned work sharePlanned maintenance hours ÷ total maintenance hoursUp
Unplanned downtimeHours lost to failures on monitored assetsDown
Cost avoidedSum of estimated failure cost minus planned repair cost for each catchUp

A simple return on investment

A first-pass business case needs only a few numbers: how many failures happen per year on the assets in scope, what an average failure costs (repair, downtime, secondary damage), what share the program will catch, and what it costs.

First-pass ROIInteractive · currency units in thousands
120 10 40k 70% 1.2k 25k
Failure cost avoided
–
Installed cost
–
Net yearly benefit
–
Payback
–
How it is calculated: each caught failure is assumed to save 75% of its cost, because a planned repair still costs something. Running cost covers analysis time, software and battery replacement. Use your own failure records; a business case built on your plant's history is far more convincing than an industry average.

Do not forget benefits that are harder to count: safety (fewer people near running machines on routes), energy (misalignment and unbalance waste power), spare parts inventory (order on condition instead of holding everything), and fewer secondary failures.

Scaling up

  • Expand by area or asset class, reusing templates for sensor placement, data settings and alarms.
  • Add techniques where the pilot showed blind spots: oil on gearboxes, ultrasound on slow bearings, motor current on remote motors.
  • Introduce machine learning once you have consistent data and feedback labels from a few months of operation.
  • Feed findings into proactive work: precision alignment, balancing and lubrication practice remove the causes that PdM keeps finding.

Key takeaways

  • Pilot 20–50 assets for 3–6 months with written success criteria.
  • Baseline before alarming; combine severity limits, statistical baselines and models.
  • Every alert needs an owner, a recommendation and a closed work order with as-found feedback.
  • Track catch rate, warning time, false alarms and cost avoided to prove value.

Plan your program

Use the PdM Program Setup app to turn your asset list into a monitoring plan with sensor counts and settings you can export.

Open PdM Program Setup